♦ Mini blast furnace to be fully operational by end-Nov/Dec 2010.
AJR’s mini blast furnace is expected to commence its full operation by
end-Nov/Dec 2010 after going through cold commissioning currently. To
recap, its mini blast furnace was originally targeted to be completed by
Dec 2008, but was subsequently delayed due to the downturn in the
global economy. In addition, the initial plan to invest into a slabs rolling
mill to produce high-grade engineering steel products has also been
shelved.